Sneak peek!

14 July 2008

The new Logan North Library is on schedule for its anticipated opening date of Monday the 4th of August. We would like to remind borrowers that the library will not be closed at anytime before the move to the new library. We will close at the normal time of 4.00pm Saturday the 2nd of August at our current premises, and reopen on the Monday at our new facility. Below is a sneak peak at what the new library will look like!

Click on a thumbnail to enlarge the image:

 

Community workspace area The story telling area Computer desks and the photocopying & printing area
14th July
Community workspace area.
14th July
The story telling area.
14th July
Computer desks and the photocopying & printing area.
     
The meeting room The Reference Desk, looking towards the Young Adult area  
14th July
The meeting room.
14th July
The Reference Desk, looking towards the Young Adult area.
 

 

The home stretch

1 July 2008

Work continues to progress on schedule for the estimated completion of the new library at the end of July, early August.

Click on a thumbnail to enlarge the image:

 

The North side of the building. Carpet's down! The Community Notices area.
1st July
The North side of the building.
1st July
Carpet’s down!
1st July
The Community Notices area.
     
The Self Serve Coffee area. A whole lot of space! The Junior area.
1st July
The Self Serve Coffee area.
1st July
The Magazine & Newpaper area.
1st July
A whole lot of space!
     
Room with a view! Stairwell. The Magazine & Newpaper area.
1st July
The Junior area.
1st July
Room with a view!
1st July
Stairwell.

 

The brand new Logan North Library

27 June 2008

The Logan North Library’s construction is coming along nicely! The new library, located on the corner of Sports Drive and Springwood Road in Underwood, will be moving location late July or early August 2008. Final moving date will be advised.

We look forward to celebrating Logan North Library’s opening in September, with many being able to enjoy the new library facilities, including:

 
  • accessibility centre
  • book clubs
  • Home Library Service
  • plasma screen with Foxtel
  • self-serve checkout
  • undercover parking
  • air-conditioning
  • children’s area
  • meeting room 
  • quiet study rooms
  • self-serve coffee station 
  • art display spaces
  • colour photocopying and printing
  • community workspace
  • school holiday programs
  • story telling

 

The countdown begins

17 June 2008

The new library is nearing completion as work continues on schedule. The partitions and wall linings have almost been completed. The joinery is 60% complete and the joinery units are 40% complete. The internal painting has commenced. The electrical services are 80% complete. The roofing and flashing are 90% complete. The lift installation has commenced. The building should have full power by Friday.

Click on a thumbnail to enlarge the image:

 

Is that ceiling curved? The junior area has a kitchen? The staff workroom.
17th June
Is that ceiling curved?
17th June
The Junior area has a kitchen?
17th June
The staff workroom.
     
Quiet study rooms. The Magazine area. The kitchen area in the meeting room.
17th June
Quiet study rooms.
17th June
The Magazine area.
17th June
The kitchen area in the meeting room.
     
The photocopy/printing area. Self serve refreshment area. View from the photocopiers.
17th June
The photocopy/printing area.
17th June
Self serve refreshment area.
17th June
View from the photocopiers.
     
Do I spy the architect?    
17th June
Do I spy the architect?
   

 

What a site!

3 June 2008

The new library continues to take shape, as we count down the weeks to the expected completion date. Logan Water is currently installing the water supply for the library. The lift will be delivered next week. Installation will take 4 - 5 weeks as the lift car is assembled in the lift well. The suspended ceiling started installation yesterday. Water proofing has been completed (99% before the heavy downfall last week - only a few leaks to deal with). The joinery work will commence next Tuesday. The storm water drainage will be completed next week. 95% of the cladding has been completed. Flooring in the activity area has commenced. General floor installation will be completed by the end of June.

Click on a thumbnail to enlarge the image:

 

The kitchen area in the meeting room. What will be the loans desk area. Two of the quiet study rooms.
3rd June
The kitchen area in the meeting room.
3rd June
What will be the loans desk area.
3rd June
Two of the quiet study rooms.
     
Upstairs meeting room. The staff workroom. The Children's area.
3rd June
Upstairs meeting room.
3rd June
The staff workroom.
3rd June
The Children’s area.
     
The hole is for our vending machine. The Young Adult area. Our picture window.
3rd June
The hole is for our vending machine.
3rd June
The Young Adult area.
3rd June
Our picture window.
     
The west side cladding. The stairway to Library Heaven. The east side cladding.
3rd June
The west side cladding.
3rd June
The stairway to Library Heaven.
3rd June
The east side cladding.

 