New Library

« Previous PageNext Page »

Here comes the library…

20 May 2008

The new Logan North Library has been coming together at an impressive rate. The wall linings and partitions have commenced. The external cladding commenced today. The roof is complete except for the lift shaft. The glazing is almost complete; there are a few internal windows left to finish. The mechanical services for the building are 99% complete. The civil drainage work commences tomorrow. The lift is due into the Port of Brisbane on the 2nd of June. It will take 4-5 weeks to install. The building will be water tight in about a week and a half.

Click on a thumbnail to enlarge the image:

 

Librarian's offices. Staff lunch room. Organised chaos.
20th May
Librarian’s offices.
20th Staff lunch room. 20th May
Organised chaos.
     
Children's area. The bits that belong in the ceiling. Some walls at last.
20th May
Children’s area.
20th May
The bits that belong in the ceiling.
20th May
Some walls at last.
     
Stair & lift well. Meeting room. Stairway to Library Heaven!
20th May
Stair & lift well.
20th May
Meeting room.
20th May
Stairway to Library Heaven!
     
Front door. Front entrance. Imposing!
20th May
Front door.
20th May
Front entrance.
20th May
Imposing!
     
Framing goes up for the outside cladding.    
20th May
Framing goes up for the outside cladding.
   

 

Progress, progress, progress…

6 May 2008

The structural steel is complete. The internal stud walls and framing have commenced along with the electrical wiring. The roofing and flashing is progressing. The downstairs joinery commences next week. The glazing on the upper floor commences this week. The wall cladding is being delivered this week and the downstairs rendering is complete.

Click on a thumbnail to enlarge the image:

 

Insulation to keep us cool. A jungle of wall framing. Air conditioning riser.
6th May
Insulation to keep us cool.
6th May
A jungle of wall framing.
6th May
Air conditioning riser.
     
Young Adult area. Going to plan! A forest of steel.
6th May
Young Adult area.
6th May
Going to plan!
6th May
A forest of steel.
     
Should be a great view. Lovely picture windows. Where are the walls?
6th May
Should be a great view.
6th May
Lovely picture windows.
6th May
Where are the walls?
     
It's going to be huge! Let's have a peek! Loans area.
6th May
It’s going to be huge!
6th May
Let’s have a peek!
6th May
Loans area.
     
Returns area. Staff work room.  
6th May
Returns area.
6th May
Staff work room.
 

 

This will be your library!

22 April 2008

Logan North Library continues to take shape. The structural steel has almost been completed. The roofing will commence this Thursday, and the roof sheeting will arrive next week. The lower level mechanical services commences next week. Glazing has been completed downstairs, and has commenced upstairs. Painting and rendering downstairs will commence next week.

Click on a thumbnail to enlarge the image:

 

Entry level. Reaching for the sky! The upper level.
22nd April
Entry level.
22nd April
Reaching for the sky!
22nd April
The upper level.
     
Hard workers in hard hats! No walls yet... Like a giant Meccano set!
22nd April
Hard workers in hard hats!
22nd April
No walls yet…
22nd April
Like a giant Meccano set!

 

A roof over our heads

10 April 2008

The new library continues to take shape. The front door of the library was fitted this week, as well as the partitions and panels for the lower floor. The blockwork for the garbage enclosure should also be completed this week. The erection of the structural steel has commenced, and will continue over the next few weeks. The lift for the library is coming from Germany and should be delivered late in June.

Click on a thumbnail to enlarge the image:

 

The library continues to grow... Eventually this will be the roof.
10th April
The library continues to grow…
10th April
Eventually this will be the roof.
   
A first glimpse of the foyer. Meet the new neighbours...
10th April
A first glimpse of the foyer.
10th April
Meet the new neighbours…

 

A little bit here, a little bit there…

1 April 2008

Construction of the new library continues to progress. The erection of the structural steel will begin next week. The windows on the ground floor are being installed and the lift for the library should be shipped later this week. The concrete slab is complete, including the stairwell, fire stairs and lift well.

Click on a thumbnail to enlarge the image:

 

Lots of space! Corner perspective. The view from the back.
28th March
Lots of space!
28th March
Corner perspective.
28th March
The view from the back.
     
Coming along nicely. Over there in the distance. Well, well, well...
28th March
Coming along nicely.
28th March
Over there in the distance.
28th March
Well, well, well…

 